A landslide in Koçtepe Village, Şırnak, necessitated urgent intervention to ensure the safety of local residents and protect the residential areas. As Sertka İnşaat, we undertook an extensive fore pile project to address this issue and prevent similar incidents in the future.
Details of the Fore Pile Work
In the area at risk of landslides, soil surveys and geotechnical analyses determined that the most suitable solution was the fore pile method. Fore piles were chosen as an effective method to increase the load-bearing capacity of the soil and prevent landslides.
Steps Implemented:
Soil Survey and Analysis: Initially, soil surveys and geotechnical analyses were conducted to identify the causes of the landslide and the necessary measures to prevent it.
Design of Fore Piles: The locations and depths of the fore piles were designed according to the needs of the project.
Pile Driving: Using specialized machinery, fore piles were driven into the designated locations, stabilizing the soil.
Control and Monitoring: Throughout and after the project, regular inspections were conducted to ensure the functionality of the fore piles and the overall success of the project.
Results of the Project
Thanks to the fore pile work carried out, the risk of a landslide recurring in Koçtepe Village has been significantly reduced. The safety of the local residents has been ensured, and a crucial step has been taken to protect the residential areas. The project was successfully completed by Sertka İnşaat's experienced and expert team and will serve as a reference for similar projects in the future.
At Sertka İnşaat, we take pride in the successful completion of this project in Koçtepe Village, Şırnak, and continue to offer our services to solve similar issues across our country.
Tags: